Updates on this issue :


2017-06-18 06:58:03

Maintenance is complete, there was minimal downtime for the change over.

2017-06-18 05:46:06

The data centre has taken some time to configure the new hardware.

Downtime has not yet occurred.

2017-06-17 23:30:04

The maintenance is still on schedule. In 1 hour and 30 minutes the datacenter will start changing the equipment.

2017-06-16 22:43:26

A quick reminder that the maintenance will start in approximately 26 hours from now. There will be a small network downtime, but the datacenter promised us to keep it as short as possible!
We will update this issue once the maintenance has started with some updates on the progress.

2017-06-13 23:18:07

On the night from saturday (17) to sunday (18) we will be performing maintenance on our network.Maintenance is scheduled from 1:00 till 3:00 (CEST TIME)
During this maintenance we will be replacing our switches with Juniper EX4200-48T's.
The switches will be connected with 2x 10Gbit connections to our network.
Our pod01 will be replaced by a Cisco Nexus 3064-T.During this maintenance, network interruptions are expected.