595 | Planned Migration from LA1 to LA2 Data Center | Datacenter | Maintenance | Resolved | 2025-02-02 14:54:26 |
Hello,
IPv6 is functioning properly now.
Please check and contact our support team if you need anything.
Regards,
CrownCloud Support Team
Hi,
The network issue has been resolved on the Dedicated server and everything is up now.
We’re currently finalizing IPv6 configurations and will provide updates as soon as they are ready.
Regards,
CrownCloud Support Team
Hello,
The migration scheduled for Sunday, January 26th, at 2:00 PM UTC (6:00 AM PST) is successfully completed within the 12-hour timeframe. All servers are now online and working as expected, with IPv4 functioning properly. We’re currently finalizing IPv6 configurations and will provide updates as soon as they are ready.
Regards,
CrownCloud Support Team
Part of the network has been restored.
We're working on to restore the remaining servers and network.
Last batch of equipments aer being moved to the new Datacenter.
Our engineers and DC technicians are configuring the Networking.
Rack #3 has arrived at the new datacenter and is being setup.
We are now starting with the migrations.
Servers are now going down, we will update as we progress.
Regards,
CrownCloud Support Team
Hello,
Due to ongoing issues and lack of transparency at our LA1 Data Center, we’ve decided to migrate all equipment and servers to our existing LA2 Data Center.
Scheduled Migration Window:
+-------------------------------------------------------------+
Date: Sunday, 26th January
Start Time: 2:00 PM UTC (6:00AM PST)
Estimated Downtime: ~12 hours
+-------------------------------------------------------------+
This move ensures improved stability and avoids future downtimes at LA1. We apologize for the inconvenience and appreciate your understanding.
We will update this space as we progress.
Regards,
CrownCloud Support Team